The federal government has revealed that the proposed national carrier, Air Nigeria, would be launched in the third quarter of this year. READ ALSO: President Buhari Approves Cut In Petrol Price
The Minister of Aviation, Senator Hadi Sirika, while briefing journalists in the State House, Abuja, after the weekly Federal Executive Council, FEC, meeting, said that the airline, at the initial stage, would take-off with its operations restricted to Nigeria.
Sirika also disclosed that the difficulties in acquiring quarry dust were the major threats to the speedy completion of the rehabilitation of the Akanu Ibiam International Airport, Enugu.
He, however, assured that despite the challenges, the project would be delivered before Easter, as scheduled.
The Minister described quarry dust as a more durable raw material than ordinary sand in the construction of runways, saying the intention is to build the most durable runway in the country, at the airport.
The contractors, according to Sirika, needed not less than 2,000 tonnes of quarry dust daily for the construction and had currently run out of the commodity in Enugu.
He further revealed that the contractors have resorted to sourcing the material from neighbouring states where he said they could only get as little as 900 tonnes per day.
In spite of the delay in finishing the project, Sirika, however, stressed that the completion date had not been shifted.
He said: “I think the main challenge we have in Enugu is the quarry dust. This quarry dust in the design of Enugu runway, so that we will get a very strong runway better than any other runway in the country.
“We decided to change sand to quarry dust. Now that quarry dust we will be requiring 1,500 tonnes every day. If we are going to work day and night, we will be requiring 2,500 tonnes of quarry dust every day.
“Now, we have exhausted all the quarries in and around Enugu, we are getting about sometimes 900 tonnes. We are going into the neighbouring states to be scouting for this quarry dust.
“I am confident that we will continue to get the quarry dust even if it means to pay extra for transportation. And if we are getting that quarry dust we will deliver this project before Easter 2020, and by God’s grace, we will continue and get this quarry dust, it has been a challenge since we started.”